


Location: Christchurch
Project Manager: Iain Haycock (100% tenure)
Site Manager: Harley Winchester (50% tenure)
McMillan SDS was successful in tendering for the construction of the abstraction and re-injection bores for the University of Canterbury Air conditioning Project.
The works consisted of constructing a 300NB abstraction bore to a depth of 200mbgl and two 300NB re-injection bores to 60mbgl. The positioning of the bores close to large multi-storey buildings, the presence of artesian aquifers, stringent environmental conditions and university activities required careful consideration during construction. Precautions included installing pre-collars to isolate foundation vibrations during drilling and pressure grouting at depth to contain the potentially high artesian and re-injection pressures. Rotary and Cable Tool methods were adopted for this project given the site constraints and potential for above ground artesian aquifers.
Considerable attention was placed on the removal of discoloured water during the construction phase and the contract allowed for 1,000m3 of water to be transported offsite at considerable expense. To avoid this cost, McMillan SDS successfully constructed and operated a temporary 300m3 settlement and filter tank system to treat all water prior to discharge into Okeover Stream, negating the need for offsite disposal.
The contract was completed during the University Christmas vacation on time and on budget. The abstraction bore now delivers cool water (approximately 14 degrees Celcius) from a deep aquifer to the air conditioning plant prior to re-injection into a shallow aquifer via the re-injection bores.
Referees
Location: Loop Road, Queenstown, New Zealand
Client: The Central Heating Company Ltd
McMillan SDS were contracted to drill 3 x 100m deep at 150mm diameter bores, assit with loop installation, and conduct the loop grouting for a new house being built on the shores of Lake Wakatipu. The project had limited access, and the upper 6-12m of the ground encountererd was soft silts and gravels that required temporary casing to be installed. We selected out HD180 twin rotary rig for the contract, and successfully completed the contract on time and budget despite fractured rock and significant ground water being encountered.
Referee120 High Street, Southbridge, Canterbury, New Zealand
ph: +64 3 324 2571 Contact Us Click Here.